Question: Amelio Rodriguez Computing wants to establish an assembly line for producing a new product, the Personal Digital Assistant ( PDA ) . The tasks, task

Amelio Rodriguez Computing wants to establish an assembly line for producing a new product, the Personal Digital Assistant(PDA). The tasks, task times, and immediate predecessors for the tasks are as follows:
Task
Time
(sec)
Immediate Predecessor
A
11
minus
B
14
A
C
8
A
D
4
B, C
E
20
D
Amelio's goal is to produce 170 PDAs per hour.
Part 2
a) The cycle time for the production of a PDA=
enter your response here seconds (round your response to two decimal places).
Part 3
b) The theoretical minimum number of workstations that Amelio can achieve in this assembly lineequals
enter your response here (round your response up to the next whole number).
Part 4
c) For one to assign the tasks to the actual workstations and be able to use the "theoretical minimum" number, the activity assignment should be:
Part 5Part 6
Workstation #
Tasks Assigned to Workstation
1
A
C
E
B
D
2
B
B
C
E
D
3
E
C
B
D
Part 7
Were you able to assign all the tasks to the theoretical minimum number of workstations?
No
Yes

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!