Question: Amelio Rodriguez Computing wants to establish an assembly line for producing a new product, the Personal Digital Assistant (PDA). The tasks, task times, and immediate

Amelio Rodriguez Computing wants to establish an assembly line for producing a new product, the Personal Digital Assistant (PDA). The tasks, task times, and immediate predecessors for the tasks are as follows:Amelio Rodriguez Computing wants to establish an assembly line for producing a

Amelio's goal is to produce 175 PDAs per hour.

Part 2

The time available to produce the required quantity = ___ seconds (enter your response as a whole number).

Part 3

The cycle time for the production of a PDA = ___ seconds (round your response to two decimal places).

Part 4

The total operational time for the complete process = ___ seconds (enter your response as a whole number).

Part 5

The theoretical minimum number of workstations that Amelio can achieve in this assembly

line = ___ (round your response to the immediate higher whole number).

Part 6

For one to assign the tasks to the actual workstations and be able to use the "theoretical minimum" number, the activity assignment should be:

Workstation # Tasks Assigned to Workstation
1 A ???
2 B ???
3 ???

Were you able to assign all the tasks to the theoretical minimum number of workstations?

No

Yes

\begin{tabular}{ccc} \hline Task & \begin{tabular}{c} Time \\ (sec) \end{tabular} & \begin{tabular}{c} Immediate \\ Predecessor \end{tabular} \\ \hline A & 12 & - \\ B & 14 & A \\ C & 8 & A \\ D & 5 & B, C \\ E & 18 & D \\ \hline \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!