Question: An activity, A, has two succeeding activities, B and C. Given the following information, determine the latest starting time for activity A. EF B =40,

An activity, A, has two succeeding activities, B

An activity, A, has two succeeding activities, B and C. Given the following information, determine the latest starting time for activity A. EF B =40, EF C = 42, LF B =43, LF C = 53; activity times are A = 4, B = 6, C = 8 O a. 32 O b. 35 O c. 37 O d. 33 e. Insufficient information