Question: An activity based costing system is used at GCO Plc Ltd. to assign products overhead costs. First, the two overhead costs of Building Maintenance expense

An activity based costing system is used at GCO Plc Ltd. to assign products overhead costs. First, the two overhead costs of Building Maintenance expense and Equipment depreciation are allocated to three activity cost pools - Finishing, Order Filling, and Other - based on resource consumption. The information used to perform these allocations is below:

Overhead Costs:

  • Building Maintenance expense: $100,000
  • Equipment depreciation: $175,000

Distribution of Resource Consumption across Activity Cost Pools:

Overhead Cost Activity Cost Pools
Finishing Order Filling Other
Building Maintenance expense 0.22 0.26 0.52
Equipment depreciation 0.48 0.44 0.08

The second stage of allocation is done by assigning the Finishing costs to products on the basis of direct labor hours while products are assigned Order Filling costs based on orders filled. Costs assigned to the Other activity pool are not further assigned to products. Activity information for GCO's only two products is below:

direct labor hours orders filled
Product LS-172: 5,000 1,700
Product LS-137: 2,200 2,600
Total: 7,200 4,300

PART A:

How much overhead cost is assigned to the Finishing activity cost pool under activity based costing in the first stage of allocation?Answer

PART B:

The activity rate for the Finishing activity cost pool under activity based costing is closest to:Answer

PART C:

What is the overhead cost assigned to Product LS-172 under activity based costing?Answer

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!