Question: An activity diagram for a construction project is given. ( Activity letters and durations are shown along each path, and milestones are inside each node

An activity diagram for a construction project is given. (Activity letters and durations are shown along each path, and milestones are inside each node circle.)
What is the float of activity E?
A.0 days
B.1 day
C.2 days
D.3 days
 An activity diagram for a construction project is given. (Activity letters