Question: An activity has the below estimates: 1 1 weeks for optimistic time 1 7 weeks for most likely time 2 3 weeks for pessimistic time.

An activity has the below estimates:
11 weeks for optimistic time
17 weeks for most likely time
23 weeks for pessimistic time.
What is the expected value of the activity time?
Your Answer: