Question: An activity on a PERT network has these time estimates: optimistic = 1, most likely = 2, and pessimistic = 5. Its expected time is
An activity on a PERT network has these time estimates: optimistic = 1, most likely = 2, and pessimistic = 5. Its expected time is
Select one:
A. 2.00.
B. 23.3.
C. 8.00.
D. 2.33.
E. 2.67.