Question: An activity on a PERT network has these time estimates: optimistic = 2, most likely = unknown, and pessimistic = unknown. If variance = 2.25

An activity on a PERT network has these time

An activity on a PERT network has these time estimates: optimistic = 2, most likely = unknown, and pessimistic = unknown. If variance = 2.25 and expected time = 7.5, what are the most likely and pessimistic estimates? 5, 12 6,9 5, 11 8, 11 8, 12

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!