Question: An activity on a project has Earliest Finish Time (EFT) of 55 days, Latest Start Time (LST) of 33 days. If the activity has the
An activity on a project has Earliest Finish Time (EFT) of 55 days, Latest Start Time (LST) of 33 days. If the activity has the duration of 10 days, what is the Slack for this activity?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts