Question: An agile development team is working on a software project. At this point, they finished two sprints and about to start the third sprint and
- An agile development team is working on a software project. At this point, they finished two sprints and about to start the third sprint and they are trying to estimate the product release date. They used planning poker and assigned user story points to their backlog items. They have been following 2-week sprints.
Based on their progress so far and the product backlog given below, how many weeks would it take them to finish the product? Explain your answer (10 pts)
| Product backlog | Story points |
| Item 1 | 2 |
| Item 2 | 8 |
| Item 3 | 13 |
| Item 4 | 5 |
| Item 5 | 5 |
| Item 6 | 8 |
| Item 7 | 1 |
Completed sprints
| Sprint | Story points |
| 1 | 10 |
| 2 | 16 |
| 3 |
|
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock