Question: An agile development team is working on a software project. At this point, they finished two sprints and about to start the third sprint and

  1. An agile development team is working on a software project. At this point, they finished two sprints and about to start the third sprint and they are trying to estimate the product release date. They used planning poker and assigned user story points to their backlog items. They have been following 2-week sprints.

Based on their progress so far and the product backlog given below, how many weeks would it take them to finish the product? Explain your answer (10 pts)

Product backlog

Story points

Item 1

2

Item 2

8

Item 3

13

Item 4

5

Item 5

5

Item 6

8

Item 7

1

Completed sprints

Sprint

Story points

1

10

2

16

3

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!