Question: An alternative plan for use in case the original plan does not work out is known as a(n):alternative plan.contingency plan.standing plan.single-use plan.day-by-day plan.
An alternative plan for use in case the original plan does not work out is known as a(n):alternative plan.contingency plan.standing plan.single-use plan.day-by-day plan.