Question: An analyst estimated that there will be an 38% learning rate for a computer assembly operation. From previous experience he knows that new hires often

  1. An analyst estimated that there will be an 38% learning rate for a computer assembly operation. From previous experience he knows that new hires often take 48 minutes to perform the first assembly and the standard time is set at 4.5 minutes (Value 20 points)
    1. How many cycles are needed to reach the standard time?
    2. How long will it take the operator to reach the standard time?