Question: An approach to creating a work breakdown structure for a project that starts with smaller tasks or units of work and then groups them into

An approach to creating a work breakdown structure for a project that starts with smaller tasks or units of work and then groups them into progessively larger, homogeneous units until it arrives at the entire project as a single unit is the: Group of answer choices top-down approach analogy approach guideline approach bottom-up approach