Question: An appropriate sequence for risk management activities is: A . Risk identification, risk quantification, and risk response development and control. B . Risk identification, risk
An appropriate sequence for risk management activities is:
A Risk identification, risk quantification, and risk response development and control.
B Risk identification, risk assessment, and risk planning.
C Risk identification, risk mitigation, and risk management.
D Risk identification, risk elimination, and risk mitigation.