Question: An assembly line has 6 work stations with cycle time of 6 minutes.There are 10 tasks with total work content of 12 minutes. What is

An assembly line has 6 work stations with cycle time of 6 minutes.There are 10 tasks with total work content of 12 minutes. What is approximate efficiency of this line?

0.33

0.50

0.67

0.80