Question: An assembly line has to perform 1 0 work elements, whose time requirements follow. An operations analyst has found a solution using some heuristics, as

An assembly line has to perform 10 work elements, whose time requirements follow. An operations analyst has found a solution using some heuristics, as shown in the table. If the cycle time of the line is 98 seconds, what is the efficiency of the assembly line?