Question: An assembly line is to be designed to operate 7 ( 1 ) / ( 2 ) hours per day and supply a steady demand

An assembly line is to be designed to operate 7(1)/(2) hours per day and supply a steady demand of 300 units per day. Here are the tasks and their performance times: [[Task,Preceding Tasks,Performance Time (Seconds)],[a,-,70],[b,-,40],[c,-,45],[d,a,10],[e,b,30],[f,c,20],[g,d,60],[h,e,50],[i,f,15],[j,g,25],[k,h, i,20],[I,j, k,25]] c. What is the theoretical minimum number of workstations?