Question: An assembly line is to be designed to operate 8 . 2 5 hours per day and supply a steady demand of 2 7 5
An assembly line is to be designed to operate hours per day and supply a steady demand of units per day. Here are the tasks and their performance times:
b What is the workstation cycle time required to produce units per day?
c What is the theoretical minimum number of workstations?
Note: Round up your answer to the next whole number.
Minimum number of workstations
d Assign tasks to workstations using the longest operating time.
Note: Leave no cells blank be certain to enter wherever required.