Question: An assembly line is to be designed to operate 8 hours per day and supply steady demand of 480 units per day. Below are the
An assembly line is to be designed to operate 8 hours per day and supply steady demand of 480 units per day. Below are the tasks and their performance times:
| Task | Preceding Task | Activity Time (Seconds) | Task | Preceding Task | Activity Time (Seconds) |
| A | - | 28 | G | F | 23 |
| B | - | 13 | H | F | 25 |
| C | B | 35 | I | G | 37 |
| D | A | 11 | J | G, H | 11 |
| E | C | 20 | K | I, J | 27 |
| F | D, E | 6 | Total |
| 236 |
- Draw the precedence diagram.
- Find the required cycle time for meeting the daily demand.
- What is the theoretical minimum number of workstations? Assign tasks to each workstation. Show your task assignment on the diagram shown in part (a).
- What is the efficiency of your line balancing as shown in part (c)?
- What would you do if the demand decreases by 50% to 240 units per day?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock