Question: An assembly line is to be designed to operate 8.5 hours per day and supply a steady demand of 275 units per day. Here are

An assembly line is to be designed to operate 8.5 hours per day and supply a steady demand of 275 units per day. Here are the tasks and their performance times:

TASK PRECEDING TASKS PERFORMANCE TIME (SECONDS)
A 60
B 28
C 20
D A 50
E B 55
F C 58
G D 30
H E 60
I F 10
J G 25
K H, I 67
L J, K 30

d.Assign tasks to workstations using the longest task time.

Note: Leave no cells blank - be certain to enter "0" wherever required.

An assembly line is to be designed to operate 8.5 hours per

d. Assign tasks to workstations using the longest task time. Note: Leave no cells blank - be certain to enter "0" wherever required

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!