Question: An assembly line is to be designed to operate 8.5 hours per day and supply a steady demand of 275 units per day. Here are
An assembly line is to be designed to operate 8.5 hours per day and supply a steady demand of 275 units per day. Here are the tasks and their performance times:
| TASK | PRECEDING TASKS | PERFORMANCE TIME (SECONDS) |
|---|---|---|
| A | 60 | |
| B | 28 | |
| C | 20 | |
| D | A | 50 |
| E | B | 55 |
| F | C | 58 |
| G | D | 30 |
| H | E | 60 |
| I | F | 10 |
| J | G | 25 |
| K | H, I | 67 |
| L | J, K | 30 |
d.Assign tasks to workstations using the longest task time.
Note: Leave no cells blank - be certain to enter "0" wherever required.

d. Assign tasks to workstations using the longest task time. Note: Leave no cells blank - be certain to enter "0" wherever required
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock