Question: An assembly line operates 7.5 hours per day with a demand of 200 units per day. The activities and their task times that go into

An assembly line operates 7.5 hours per day with a demand of 200 units per day. The activities and their task times that go into the production of a unit are as follows:

Activity

Precedent

Activity Times (minutes)

A

5

B

A

4

C

B

9

D

B

10

E

C

3

F

E

2

G

D

6

H

G

5

I

F, H

3

  1. Draw the precedence diagram. What is the process task time? What is the total labor content for a unit of product?
  2. What is the Cycle time (takt time) for the demand of 200 units per day? Interpret this number.
  3. What is the theoretical minimum number of workstations?
  4. Assign tasks to workstations using the longest operating time.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!