Question: An assembly line operates 7.5 hours per day with a demand of 200 units per day. The activities and their task times that go into
An assembly line operates 7.5 hours per day with a demand of 200 units per day. The activities and their task times that go into the production of a unit are as follows:
| Activity | Precedent | Activity Times (minutes) |
| A |
| 5 |
| B | A | 4 |
| C | B | 9 |
| D | B | 10 |
| E | C | 3 |
| F | E | 2 |
| G | D | 6 |
| H | G | 5 |
| I | F, H | 3 |
- Draw the precedence diagram. What is the process task time? What is the total labor content for a unit of product?
- What is the Cycle time (takt time) for the demand of 200 units per day? Interpret this number.
- What is the theoretical minimum number of workstations?
- Assign tasks to workstations using the longest operating time.