Question: An assembly line with 17 tasks is to be balanced. The longest task is 2.9 minutes, and the total time for all tasks is 14
An assembly line with 17 tasks is to be balanced. The longest task is 2.9 minutes, and the total time for all tasks is 14 minutes. The line will operate for 452 minutes per day. a. What are the minimum and maximum cycle times? (Round your answers to 1 decimal place.)
Minimum cycle time ? minutes
Maximum cycle time ? minutes
b. What range of output is theoretically possible for the line? (Round your answers to whole numbers.)
Minimum output ? units per day
Maximum output ? units per day
c. What is the minimum number of workstations needed if the maximum output rate is to be sought? (Round your answer up to a whole number.)
Minimum number of workstations ? d. What cycle time will provide an output rate of 124 units per day? (Round your answer to 1 decimal place.)
Cycle time ? minutes per cycle e. What output potential will result for the following cycle times? (Round your answers to whole numbers.)
10 minutes ? units per day
15 minutes ? units per day
Should the units be rounded up?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
