Question: An assembly line with 19 tasks is to be balanced. The longest task is 27 minutes, and the total time for all tasks is 15

An assembly line with 19 tasks is to be balanced.
An assembly line with 19 tasks is to be balanced. The longest task is 27 minutes, and the total time for all tasks is 15 minutes. The line will operate for 442 minutes per day. a. What are the minimum and maximum cycle times? (Round your answers to 1 decimal place.) Minimum cycle time Maximum cycle time minutes minutes b. What range of output is theoretically possible for the line? (Round your answers to whole numbers.) Minimum output Maximum output