Question: An assembly line with 8 tasks is to be balanced. The longest task is 1 0 minutes, and the total time for all tasks is
An assembly line with tasks is to be balanced. The longest task is minutes,
and the total time for all tasks is minutes. The line will operate for minutes per day.
Round up your answers to the nearest whole number
a What is the maximum output
rates The most that can possibly
be made in a day
b What is the minimum output
rate?
c What cycle time will provide an
output rate of units per day?
Use you answer for part d
d What is the minimum number of
workstations needed if the output
rate requested was a day?