Question: An assembly operation is to be done in a single shift, 8 hours per day and 10% allowed for breaks (PF&D). The operators are expected
An assembly operation is to be done in a single shift, 8 hours per day and 10% allowed for breaks (PF&D). The operators are expected to have an 85% performance and the following parts are required:
Part X, requirement is 10,000 per week, at 100% one operator can produce 150 pieces per hour.
Part Y, requirement is 15,000 per week, at 100% one operator can produce 220 pieces per hour.
Part Z, requirement is 20,000 per week, at 100% one operator can produce 275 pieces per hour.
QUESTIONS TO ANSWER:
3. Assuming no setup time, how many people are needed to meet production requirements?
4. How many people are needed if performance is expected to be only 75%?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
