Question: An assembly operation is to be done in a single shift, 8 hours per day and 10% allowed for breaks (PF&D). The operators are expected

An assembly operation is to be done in a single shift, 8 hours per day and 10% allowed for breaks (PF&D). The operators are expected to have an 85% performance and the following parts are required:

Part X, requirement is 10,000 per week, at 100% one operator can produce 150 pieces per hour.

Part Y, requirement is 15,000 per week, at 100% one operator can produce 220 pieces per hour.

Part Z, requirement is 20,000 per week, at 100% one operator can produce 275 pieces per hour.

QUESTIONS TO ANSWER:

3. Assuming no setup time, how many people are needed to meet production requirements?

4. How many people are needed if performance is expected to be only 75%?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!