Question: An auditor identified a significant deficiency in internal control in December. The client was informed and the client corrected the significant deficiency shortly before year
An auditor identified a significant deficiency in internal control in December. The client was informed and the client corrected the significant deficiency shortly before yearend December ; the auditor agrees that the correction eliminated the significant deficiency as of December The appropriate audit report on internal control under a PCAOB Standard No audit of internal control is:
Multiple Choice
Adverse.
Unqualified.
Unqualified with explanatory language relating to the significant deficiency.