Question: A(n) ________ constraint addresses the sequence in which project activities must occur even after considering resource constraints. Group of answer choices predecessor serial successor hard
A(n) ________ constraint addresses the sequence in which project activities must occur even after considering resource constraints. Group of answer choices predecessor serial successor hard technical