Question: An ECC Option C contract has been awarded for the construction of a concert arena. The access to the Site is constrained significantly and results

An ECC Option C contract has been awarded for the construction of a concert arena.

The access to the Site is constrained significantly and results in theContractorhaving to decant the fill material into small dumper trucks from the delivery wagons. The Works Information provided by theEmployerwas clear about the access constraints.

The original Works Information was, in hindsight, poorly drafted in certain areas. Whilst theContractoris responsible for design, the Works Information did not contain a requirement for the submission of design in accordance with clause 21.2. The newly appointedSupervisornow wants to see the design of the permanent foundations and steelwork.

d.

Can theSupervisorinstruct this? How can the design be verified before work commences?

[6 marks]

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!