Question: An engineering company has 80% learning effect and spends 1000 hours to produce 1 lot of the product. Estimate the labor cost of producing 8
An engineering company has 80% learning effect and spends 1000 hours to produce 1 lot of the product. Estimate the labor cost of producing 8 lots of the product if the labour cost is Rs. 40 per hour.