Question: An estimate for an activity duration is provided based on a set rate of 2 hours per unit. Your project requires 6 0 units, therefore

An estimate for an activity duration is provided based on a set rate of 2 hours per unit. Your project requires 60 units, therefore 120 hours. This is an example of what type of estimation technique:
Group of answer choices
Parametric
analogous
Three-Point - Triangular
Three-Point - Beta