Question: An estimate for an activity duration is provided based on a set rate of 2 hours per unit. Your project requires 6 0 units, therefore
An estimate for an activity duration is provided based on a set rate of hours per unit. Your project requires units, therefore hours. This is an example of what type of estimation technique:
Group of answer choices
Parametric
analogous
ThreePoint Triangular
ThreePoint Beta
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock