Question: An estimator uses unadjusted RS Means data for a school project that will require extensive new embedded technology. What is the impact on risks for

An estimator uses unadjusted RS Means data for a school project that will require extensive new embedded technology. What is the impact on risks for the estimate? Group of answer choices Risk is increased No impact Risk is decreased Estimators judgement must be trusted