An ex-gratia claim made when a project is closed down is made when:
Question 1 options:
The project company fails to perform to the terms of the contract.
There is no contractual basis for a claim.
The client company fails to perform to the terms of the contract.
A third party causes either the client or project company to fail to perform to the terms of the contract