Question: An industrial process simulation involves five steps which are performed sequentially on system A. The steps 1 and 2 take 1 and 2 minutes respectively

An industrial process simulation involves five steps which are performed sequentially on system A. The steps 1 and 2 take 1 and 2 minutes respectively whereas steps 3 - 5 take 3 minutes each. Then system A was enhanced by introducing some parallelism to get a system B. The steps 3 to 5 on B now can be executed in parallel so that they take an overall time of 4 minutes whereas steps 1 and 2 are still to be executed in sequence. Calculate speedup using appropriate form of Amdahl's law