Question: An initial time study was done on a process with the following results (in minutes). Based on the data obtained so far, assuming an allowance
An initial time study was done on a process with the following results (in minutes). Based on the data obtained so far, assuming an allowance of 20 percent of the normal time, what do you estimate for the time per customer served, based on this preliminary sample? (Round all intermediate calculations to two decimal places.)
The time per unit customer served is _____ minutes. (Enter your response rounded to two decimal places.)
| Element | Performance Rating | Obs 1 | Obs 2 | Obs 3 | Obs 4 | Obs 5 |
|---|---|---|---|---|---|---|
| Element 1 | 70 | 3 | 6 | 4 | 6 | 6 |
| Element 2 | 120 | 9 | 11 | 8 | 8 | 9 |
| Element 3 | 80 | 6 | 8 | 6 | 8 | 7 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts