An interim dean needs help from three assistant deans. Each person can do only one task and each task should be done by only one person. The estimated time for Dean and each Assistant Dean to do each task is given in the matrix below.

Assessment (A)

Budget (B)

Curriculum (C)

Development (D)

Dean 0

42

48

40

43

Assistant Dean 1

44

54

42

45

Assistant Dean 2

48

50

64

47

Assistant Dean 3

46

56

64

72

Which of the following constraints represents the assignment for the curriculum task?

a. X0C + X1C + X2C + X3C 1

b. X0C + X1C + X2C + X3C = 0

c. X0C + X1C + X2C + X3C = 1

d. X0C + X1C + X2C + X3C 1

e. None of the above

Which of the following constraints represents the assignment for Assistant Dean 2?

a. X2A + X2B + X2C + X2D 1

b. X2A + X2B + X2C + X2D = 0

c. X2A + X2B + X2C + X2D = 1

d. X2A + X2B + X2C + X2D 0

e. None of the above

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!