Question: An internal process was recently introduced by the management team. The new process, however, has not added much value and is impacting the project's deliverables.What
An internal process was recently introduced by the management team. The new process, however, has not added much value and is impacting the project's deliverables.What should the project manager doA Allocate one team member who can focus only on process adherence.B Ensure that the team implements the process without delays in deliverables.C Discuss this with the team and convince them to continue with the process.D Negotiate with management and get the required process changed.