Question: An NEC 4 Engineering and Construction Contract Option A including secondary Option X 8 , X 1 3 and X 1 5 has been awarded
An NEC Engineering and Construction Contract Option A including secondary Option X X and X has been awarded for the construction of a new water treatment plant. The Scope states the Contractor is to design the whole of the works. The Contractor plans to subcontract a substantial amount of the work and appoint a consultant to carry out the design.The Condition for a Key Date has not been met by the date stated. Which ONE of the following best describes the actions now required by the Project Manager?