Question: An operations manager is trying to determine a production plan for the next week. There are three products ( say , P , Q ,

An operations manager is trying to determine a production plan for the next week.
There are three products (say, P, Q, and R) to produce using four machines (say, A and B, C, and
D). Each of the four machines performs a unique process. There is one machine of each type, and
each machine is available for 2400 minutes per week. The unit processing times for each
machine is given below:
Machine Product P Product Q Product R Availability
(minutes)
A 2010102400
B 1228162400
C 156162400
D 101502400
Total processing
time 5759429600
The unit revenues and maximum sales for the week are indicated in the following table: Item Product P Product Q Product R
Revenue per unit $90 $100 $70
Material cost per unit $45 $40 $20
Profit per unit $45 $60 $50
Maximum sales 1004060
Storage from one week to the next is not permitted. The operating expenses associated with the
plant are $6000 per week, regardless of how many components and products are made. The
$6000 includes all expenses except for material costs. The operations management wants to find
the best product mix. Help him/her formulate the problem as a mathematical program.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!