Question: An order for 2 5 0 bell ringers is processed on work centers 1 0 and 2 0 . The setup and run times are
An order for bell ringers is processed on work centers and The setup and run times are as follows. It is decided to overlap the lot on the two work centers and to split the lot into two lots of and Move time between operations is min utes. Work center cannot be set up until the first lot arrives. Calculate the saving in manufacturing lead time.
Setup on A minutes Run time on A minutes per piece Setup on B minutes Run time on B minutes per piece
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock