Question: An order with the smallest total set - up time and run time should be scheduled: Group of answer choices first, if we want to
An order with the smallest total setup time and run time should be scheduled:
Group of answer choices
first, if we want to minimize mean flow time
last, if the order has the latest operation due date
last, under any priority rule
first, if low average lateness is desired