Question: An organization implemented a fixed order quantity material management system. The average daily demand is 36 units. The lead time is 6 days. The safety
An organization implemented a fixed order quantity material management system. The average daily demand is 36 units. The lead time is 6 days. The safety stock was set at 200 units.
Determine the reorder point and round to the nearest whole unit, if applicable.