Question: An S-curve CANNOT be used to: Select one: a. Determine whether the project is ahead of budget b. Determine when the project is behind budget

An S-curve CANNOT be used to:

Select one:

a. Determine whether the project is ahead of budget

b. Determine when the project is behind budget

c. Determine the cause of positive variance

d. Determine whether there is negative variance