Question: Analyse the case below using SHORT - CYCLE PROCESS in project management. Analyse the case below using LONG - CYCLE PROCESS in project management. CASE
Analyse the case below using SHORTCYCLE PROCESS in project management.
Analyse the case below using LONGCYCLE PROCESS in project management.
CASE SYNOPSIS
After years at Design Prototypes, Inc., Raef Conley is leading his first major project team. Raef has assembled a highly qualified, diverse yet cohesive team and has the full support of his boss on the project, the regional Electrical Engineering EE Director, Jonathon Wright. It has been almost months since the Alpha C project was green lighted by top management. Raef and other members of the project team have met several times during those months to track the progress of the project activities and from Raefs perspective the team works well together and is still highly motivated. Initially, the project was envisioned as taking a year and a half days to complete. However, Raef and his team had developed a Work Breakdown Schedule WBS that projected completion in days, giving the team days of slack time. Developing a day plan was a very fortunate decision, as at this point the project is in the concluding stage of activity K product testing and due to unforeseen delays the days of slack time have been expended. Thus the team is using the day WBS for the just under one year remaining to complete the project. Top management is requesting that the project be shorted by a month day schedule or preferably two months day schedule In addition, the VP of Engineerings son, Simon, has been added as a team member. Simon, who has been with the company only years and lacks technical qualifications, is attempting to use the project as a way to demonstrate his value to upper management. Therefore, Simons agenda is very different from that of the other team members, creating a source of conflict. The case revolves around the questions of: Can the team develop workable shortened time schedules for completing the project in and days? Are the added costs of reducing the schedule economically sound? How do Raef and the other team members cope with the late addition of a divisive, politically connected team member?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
