Question: Analysis of a PERT problem shows the estimated (average) time for the critical path to be 108 days with a standard deviation of 8 days.

Analysis of a PERT problem shows the estimated

Analysis of a PERT problem shows the estimated (average) time for the critical path to be 108 days with a standard deviation of 8 days. There is a 0.90 probability that the project will be completed after approximately day