Question: Lily recently had a huge surge in customer demand. Her demand is now 4,532 animals a week. She has no setup time for the animals
Lily recently had a huge surge in customer demand. Her demand is now 4,532 animals a week. She has no setup time for the animals but her processing time is 2 mins per stuffed animal. She has no time to hire new employees, so she still only has 3 employees, who work 8 hours a day for 4 days each week. Calculate Lily's capacity cushion for a week?