Question: Analytics Exercise 2 1 - 2 ( Algo ) Recently, Phil Harris, the production control manager at Brunswick, read an article on time - phased
Analytics Exercise Algo
Recently, Phil Harris, the production control manager at Brunswick, read an article on timephased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of timephased requirements planning.
Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model engine. This schedule indicates the number of units of the Model engine to be assembled each week during the last weeks and is shown in the figure given below. Next, Phil decided to simplify his requirements planning example by considering only two of the many components needed to complete the assembly of the Model engine. These two components, the gear box and the input shaft, are shown in the product structure diagram. Phil noted that the gear box is assembled by the Subassembly Department and subsequently is sent to the main engine assembly line. The input shaft is one of several component parts manufactured by Brunswick needed to produce a gear box subassembly. Thus, levels and are included in the product structure diagram to indicate the three manufacturing stages involved in producing an engine: the Engine Assembly Department, the Subassembly Department, and the Machine Shop.
The manufacturing lead times required to produce the gear box and input shaft components are also indicated in the product structure diagram. Note that two weeks are required to produce a batch of gear boxes and that all the gear boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of input shafts, and all the shafts needed for the production of gear boxes in a given week must be delivered to the Subassembly Department stockroom before Monday morning of that week.
In preparing the MRP example, Phil planned to use the worksheets shown and to make the following assumptions:
Twenty two gear boxes are onhand at the beginning of Week and eight gear boxes are currently on order to be delivered at the start of Week
Forty five input shafts are onhand at the start of Week and are scheduled for delivery at the beginning of Week
Initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and plannedorder releases for the gear boxes and input shafts. Assume that lot sizing is done using lotforlot LL
Note: Leave no cells blank be certain to enter wherever required.
Gear Box Requirements
Input Shaft Requirements
Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. These costs are as follows:
PARTCOSTGear BoxSetup $order Inventory carrying cost $unitweekInput ShaftSetup $order Inventory carrying cost $unitweek
Given the cost structure, evaluate the cost of the schedule from a Assume inventory is valued at the end of each week.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock