Analytics Exercise 21-3 (Algo) Recently, Phil Harris, the production control manager at Brunswick, read an article...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
Analytics Exercise 21-3 (Algo) Recently, Phil Harris, the production control manager at Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule Indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown on the next page. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram below. Phil noted that the gear box is assembled by the Subassembly Department and subsequently is sent to the main engine assembly line. The input shaft is one of several component parts manufactured by Brunswick that are needed to produce a gear box subassembly. Thus, levels 0, 1, and 2 are included in the product structure diagram to indicate the three manufacturing stages that are involved in producing an engine: the Engine Assembly Department, the Subassembly Department, and the Machine Shop. The manufacturing lead times required to produce the gear box and Input shaft components are also indicated in the product structure diagram. Note that two weeks are required to produce a batch of gear boxes and that all the gear boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of input shafts, and all the shafts that are needed for the production of gear boxes in a given week must be delivered to the Subassembly Department stockroom before Monday morning of that week. In preparing the MRP example Phil planned to use the worksheets shown and to make the following assumptions: 1. Fifteen gear boxes are on hand at the beginning of Week 1, and five gear boxes are currently on order to be delivered at the start of Week 2. 2. Thirty six Input shafts are on hand at the start of Week 1, and 22 are scheduled for delivery at the beginning of Week 2. Week Model 1000 master schedule 1 2 3 4 5 6 7 8 9 Demand 12 5 7 10 11 12 10 15 23 10 12 8 18 Crankcase Model 1000 product structure Engine assembly Gear box Lead time=2 weeks Used: 1 per engine Input shaft Lead time 3 weeks Used: 2 per gear box a. Initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for single period. Calculate the net requirements and planned order releases for the gear boxes and Input shafts. Assume that lot sizing is done using lot-for-lot (L4L). (Leave no cells blank - be certain to enter "O" wherever required.) Gear Box Requirements Week: Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipt Planned order release Input Shaft Requirements Week: Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipt Planned order release 2 3 4 5 6 7 8 9 10 11 12 12 5 7 10 0 15 23 10 0 12 8 18 2 3 4 5 6 7 8 9 10 11 12 Phil would like to consider the costs that his accountants are currently using for Inventory carrying and setup for the gear boxes and Input shafts. These costs are as follows: PART Gear Box COST Setup = $75/order Input Shaft Inventory carrying cost $1/unit/week Setup = $35/order Inventory carrying cost = $2/unit/week Suppose least-total-cost lot sizing is to be used. Using the planned order receipts shown below, complete the remainder of the gear box and Input shaft tables. (Leave no cells blank - be certain to enter "O" wherever required.) Gear Box Requirements Week: Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipt Planned order release Input Shaft Requirements Week: Gross requirements Scheduled receipts Projected available balance Net requirements 2 3 4 5 6 + 8 9 10 11 12 12 5 7 10 0 15 23 10 0 12 8 18 2 3 4 56 78 9 10 11 12 Planned order receipt 0 0 0 67 0 0 0 76 0 0 0 0 Planned order release c. What are the savings with the new schedule? Assume Inventory is valued at the end of each week. Cost of the schedule from part (a) Setup Cost Inventory Total Gear box Input shaft Total cost Cost of the schedule using least-total-cost lot sizing. Setup Cost Inventory Total Gear box Input shaft Total cost Savings with the new schedule. Savings Analytics Exercise 21-3 (Algo) Recently, Phil Harris, the production control manager at Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule Indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown on the next page. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram below. Phil noted that the gear box is assembled by the Subassembly Department and subsequently is sent to the main engine assembly line. The input shaft is one of several component parts manufactured by Brunswick that are needed to produce a gear box subassembly. Thus, levels 0, 1, and 2 are included in the product structure diagram to indicate the three manufacturing stages that are involved in producing an engine: the Engine Assembly Department, the Subassembly Department, and the Machine Shop. The manufacturing lead times required to produce the gear box and Input shaft components are also indicated in the product structure diagram. Note that two weeks are required to produce a batch of gear boxes and that all the gear boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of input shafts, and all the shafts that are needed for the production of gear boxes in a given week must be delivered to the Subassembly Department stockroom before Monday morning of that week. In preparing the MRP example Phil planned to use the worksheets shown and to make the following assumptions: 1. Fifteen gear boxes are on hand at the beginning of Week 1, and five gear boxes are currently on order to be delivered at the start of Week 2. 2. Thirty six Input shafts are on hand at the start of Week 1, and 22 are scheduled for delivery at the beginning of Week 2. Week Model 1000 master schedule 1 2 3 4 5 6 7 8 9 Demand 12 5 7 10 11 12 10 15 23 10 12 8 18 Crankcase Model 1000 product structure Engine assembly Gear box Lead time=2 weeks Used: 1 per engine Input shaft Lead time 3 weeks Used: 2 per gear box a. Initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for single period. Calculate the net requirements and planned order releases for the gear boxes and Input shafts. Assume that lot sizing is done using lot-for-lot (L4L). (Leave no cells blank - be certain to enter "O" wherever required.) Gear Box Requirements Week: Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipt Planned order release Input Shaft Requirements Week: Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipt Planned order release 2 3 4 5 6 7 8 9 10 11 12 12 5 7 10 0 15 23 10 0 12 8 18 2 3 4 5 6 7 8 9 10 11 12 Phil would like to consider the costs that his accountants are currently using for Inventory carrying and setup for the gear boxes and Input shafts. These costs are as follows: PART Gear Box COST Setup = $75/order Input Shaft Inventory carrying cost $1/unit/week Setup = $35/order Inventory carrying cost = $2/unit/week Suppose least-total-cost lot sizing is to be used. Using the planned order receipts shown below, complete the remainder of the gear box and Input shaft tables. (Leave no cells blank - be certain to enter "O" wherever required.) Gear Box Requirements Week: Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipt Planned order release Input Shaft Requirements Week: Gross requirements Scheduled receipts Projected available balance Net requirements 2 3 4 5 6 + 8 9 10 11 12 12 5 7 10 0 15 23 10 0 12 8 18 2 3 4 56 78 9 10 11 12 Planned order receipt 0 0 0 67 0 0 0 76 0 0 0 0 Planned order release c. What are the savings with the new schedule? Assume Inventory is valued at the end of each week. Cost of the schedule from part (a) Setup Cost Inventory Total Gear box Input shaft Total cost Cost of the schedule using least-total-cost lot sizing. Setup Cost Inventory Total Gear box Input shaft Total cost Savings with the new schedule. Savings
Expert Answer:
Posted Date:
Students also viewed these general management questions
-
Read Exhibit 10.6 carefully and answer the following question: Can a free-market system be trusted to effectively address the global concern in biodiversity loss? Why or why not? Exhibit 10.6 EXHIBIT...
-
In its 2012 annual report, which included a statement of comprehensive income, Bristol-Myers Squibb reported the following items (dollars in millions): Impairment charge............$ (1,830) Research...
-
Borke Ltd. has a credit balance of NT$320,000 in Allowance for Doubtful Accounts. The estimated bad debt expense under the percentage-of-sales basis is NT$370,000. The total estimated un-collectibles...
-
New Era Advertising provides media services for clients across the nation. New Era is presently working on four projects, each for a different client. New Era accumulates costs for each account...
-
Royal Seafood delivers fresh fin and shellfish to specialty grocery stores in the state of Oregon. The company packs a delivery truck in Corvallis and then drives in one single route to its five...
-
Huron Company produces a commercial cleaning compound known as Zoom. The direct materials and direct labor standards for one unit of Zoom are given below: Direct materials Direct labor Standard...
-
a. Calculate the standard hours per month. b. Determine the required FTEs with fringe benefits.
-
Question 1)Determine whether the set is a vector space. If it is not, identify at least one of the ten vector space axioms that fails. a) The set of all 2 2 matrices of the form [a b] C b) The set...
-
Information for Biggs Company and Charter Company are given below: Biggs Company Charter Company Shares of outstanding Common Stock on January 1, 20x1 104,000 51,000 Shares of outstanding Common...
-
Could you elucidate the nuanced dialectics between Moore's Law and Kondratiev waves within the overarching framework of the technology cycle, unraveling the intricate mechanisms by which exponential...
-
The set of all positive primes less than -1 but greater than 100. (ii) The set of all real-valued solutions for the equation x-x+x-1=0. (iii) The set of all integers divisible by 7 in the range [0,...
-
Swifty Enterprises sold $740,000 of accounts receivable to Wildhorse Factors, Inc. on a without recourse basis under IFRS, as the risks and rewards have been transferred to Wildhorse. The transaction...
-
ATV Co. began operations on March 1 and uses a perpetual inventory system. It entered into purchases and sales for March as shown in the Tableau Dashboard. Legend No Purchases or Sales Purchases...
-
Which of the following is FALSE regarding the purchasing power parity (PPP). a. The PPP is a manifestation of the law of one price b. The PPP says that a country with a higher expected inflation can...
Study smarter with the SolutionInn App