Question: Analytics Exercise 4 - 2 ( Problem 4 - 1 8 ( Static ) The following CPM network has estimates of the normal time in
Analytics Exercise Problem Static
The following CPM network has estimates of the normal time in weeks listed for the activities:
a Identify the critical path.
multiple choice
ACDFG
ACDEG
ABDEG
ABDFG
b What is the length of time to complete the project?
c Which activities have slack, and how much?
multiple choice
B weeks; E weeks.
C weeks; F weeks.
D week; E weeks.
C week; E weeks.
Here is a table of normal and crash times and costs.
ACTIVITYNORMAL TIMECRASH TIMENORMAL
COSTCRASH
COSTA$$BCDEFG
d Which activities would you shorten to cut two weeks from the schedule in a rational fashion?
multiple choice
A E
B C
A C
B D
d What would be the total incremental cost?
d Is the critical path changed?
multiple choice
Yes
No
You work for a company that makes cell phones and have been made project manager for the design of a new cell phone. Your supervisors have already scoped the project, so you have a list showing the work breakdown structure, and this includes major project activities. You must plan the project schedule and calculate project duration. Your boss wants the schedule on his desk tomorrow morning!
You have been given the information in Exhibit It includes all the activities required in the project and the duration of each activity. Also, dependencies between the activities have been identified. Remember that the preceding activity must be fully completed before work on the following activity can be started.
Your project is divided into five major subprojects. Subproject P involves developing specifications for the new cell phone. Here, decisions related to such things as battery life, size of the phone, and features need to be made. These details are based on how a customer uses the cell phone. These user specifications are redefined in terms that have meaning to the subcontractors that will actually make the new cell phone in subproject S supplier specifications. These involve engineering details for how the product will perform.
The individual components that make up the product are the focus of subproject D Subproject I brings all the components together, and a working prototype is built and tested.
Finally, in subproject V suppliers are selected and contracts are negotiated.
Exhibit : Work Breakdown Structure and Activities for the Cell Phone Design Project
MAJOR SUBPROJECTSACTIVITIESACTIVITY IDENTIFICATIONDEPENDENCYDURATION WEEKSProduct Specifications PMarket researchPOverall product specificationsPPHardwarePPSoftwarePPSupplier specifications SHardwareSPSoftwareSPProduct design DBatteryDSDisplayDSCameraDSOuter coverDD D DProduct integration IHardwareIDUser interfaceIDSoftware codingIIPrototype testingII ISubcontracting VSuppliers selectionVSSContract negotiationVI V
a Calculate the start and finish times for each activity. Leave no cells blank be certain to enter wherever required.
b Determine the minimum number of weeks for completing the project.
c Find the activities that are on the critical path for completing the project in the shortest time.
multiple choice
PPPPSDDIIV
PPPPSDDIIV
PPPPSDIIIV Correct
PPPPSDDIIV
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
