Question: Analytics Exercise 4 - 2 ( Problem 4 - 1 8 ( Static ) The following CPM network has estimates of the normal time in

Analytics Exercise 4-2(Problem 4-18(Static)
The following CPM network has estimates of the normal time in weeks listed for the activities:
a. Identify the critical path.
multiple choice 1
A-C-D-F-G
A-C-D-E-G
A-B-D-E-G
A-B-D-F-G
b. What is the length of time to complete the project?
c. Which activities have slack, and how much?
multiple choice 2
B,2 weeks; E,2 weeks.
C,2 weeks; F,3 weeks.
D,1 week; E,2 weeks.
C,1 week; E,2 weeks.
Here is a table of normal and crash times and costs.
ACTIVITYNORMAL TIMECRASH TIMENORMAL
COSTCRASH
COSTA76$7,000$8,000B215,0007,000C439,00010,200D543,0004,500E212,0003,000F424,0007,000G545,0008,000
d-1. Which activities would you shorten to cut two weeks from the schedule in a rational fashion?
multiple choice 3
A, E
B, C
A, C
B, D
d-2. What would be the total incremental cost?
d-3. Is the critical path changed?
multiple choice 4
Yes
No
)
You work for a company that makes cell phones and have been made project manager for the design of a new cell phone. Your supervisors have already scoped the project, so you have a list showing the work breakdown structure, and this includes major project activities. You must plan the project schedule and calculate project duration. Your boss wants the schedule on his desk tomorrow morning!
You have been given the information in Exhibit 4.13. It includes all the activities required in the project and the duration of each activity. Also, dependencies between the activities have been identified. Remember that the preceding activity must be fully completed before work on the following activity can be started.
Your project is divided into five major subprojects. Subproject P involves developing specifications for the new cell phone. Here, decisions related to such things as battery life, size of the phone, and features need to be made. These details are based on how a customer uses the cell phone. These user specifications are redefined in terms that have meaning to the subcontractors that will actually make the new cell phone in subproject S supplier specifications. These involve engineering details for how the product will perform.
The individual components that make up the product are the focus of subproject D. Subproject I brings all the components together, and a working prototype is built and tested.
Finally, in subproject V, suppliers are selected and contracts are negotiated.
Exhibit 4.13: Work Breakdown Structure and Activities for the Cell Phone Design Project
MAJOR SUBPROJECTS/ACTIVITIESACTIVITY IDENTIFICATIONDEPENDENCYDURATION (WEEKS)Product Specifications (P)Market researchP12Overall product specificationsP2P14HardwareP3P25SoftwareP4P35Supplier specifications (S)HardwareS1P42SoftwareS2P46Product design (D)BatteryD1S11DisplayD2S15CameraD3S11Outer coverD4D1, D2, D34Product integration (I)HardwareI1D43User interfaceI2D23Software codingI3I24Prototype testingI4I1, I34Subcontracting (V)Suppliers selectionV1S1,S210Contract negotiationV2I4, V12
a. Calculate the start and finish times for each activity. (Leave no cells blank - be certain to enter "0" wherever required.)
b. Determine the minimum number of weeks for completing the project.
c. Find the activities that are on the critical path for completing the project in the shortest time.
multiple choice
P1-P2-P3-P4-S1-D3-D4-I1-I4-V2
P1-P2-P3-P4-S1-D1-D4-I1-I4-V2
P1-P2-P3-P4-S1-D2-I2-I3-I4-V2 Correct
P1-P2-P3-P4-S1-D2-D4-I1-I4-V2

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!