Question: Analyze the following projects: Year Project M Project N Project O 0 -5,000 -6,000 -7,000 1 1,000 2,000 2,500 2 2,000 2,500 3,000 3 3,000

Analyze the following projects:

Year

Project M

Project N

Project O

0

-₹5,000

-₹6,000

-₹7,000

1

₹1,000

₹2,000

₹2,500

2

₹2,000

₹2,500

₹3,000

3

₹3,000

₹3,000

₹4,000

4

₹4,000

₹4,500

₹5,000

Requirements:

  1. Calculate the Payback Period for each project.
  2. Find the Discounted Payback Period at 11% cost of capital.
  3. Compute the NPV for each project at 11%.
  4. Identify the IRR for each project.
  5. Which project would you recommend if the firm’s required payback period is 3 years?