Question: Anand is developing a neighborhood and installing pools with all the homes. The pool installer takes six days to put in the first pool, and
Anand is developing a neighborhood and installing pools with all the homes. The pool installer takes six days to put in the first pool, and this task has a 90 percent experience curve. How long would it take to install the first five pools? a. 26.04 days b. 14.69 days c. 22.88 days d. 19.45 days